Vietnamese |  English |  中文 |  Báo In

Dau Tieng’s public capital disbursement promoted

Update: 04-08-2020 | 14:57:34

Dau Tieng district’s People’s Committee as of late July disbursed VND193.5billion or 58.7% of the year’s plan and 38.18% of the year’s adjusted plan.

In July, the district’s People’s Committee disbursed VND76.7billion in capital for basic construction and investment while putting focus on overseeing and hastening the progress of construction of works on schedule with quality ensured.

The local functional sectors also bent on compensation and site clearance. In July, they made compensation for 5 works with VND7.5billion for 40 documents.

Reported by Tieu My-Translated by K.T

Share
Tags
Dau Tieng
Quay lên trên