Lego Vietnam completes 90% of construction and installation items

Update: 07-11-2024 | 14:16:16

On November 6, Lego Group held a progress review ceremony for the construction of Lego Manufacturing Vietnam facility, announcing that 90% of the factory’s construction and installation items had been completed. The event was attended by Nguyen Van Loi, Member of the Party Central Committee and Secretary of provincial Party Committee; Vo Van Minh, Vice Secretary of provincial Party Committee and Chairman of provincial People’s Committee, along with representatives from various agencies, departments and partners.

Provincial leaders present flowers as congratulation to leaders of LEGO Manufacturing Vietnam Co., Ltd

Testing of systems, equipment and infrastructure at the factory marks a critical milestone for the project as it prepares for an inauguration in early 2025. This testing phase begins a multi-month inspection and trial process to ensure that the factory can meet strict quality and safety standards upheld across all Lego facilities worldwide when operational licensing is granted before the opening in early 2025.

Delegates perform the ceremony of pressing the button to test the factory

Jesper Hassellund Mikkelsen, Senior Vice President of Asia Operations and General Manager of Lego Manufacturing Vietnam stated that the testing and calibration of plastic injection machines and packaging lines at the factory represent a significant milestone, indicating that the project remains on schedule. This is possible thanks to the support of central and local ministries, agencies and the companionship of partners and staff.

At the event, Mr. Minh said that provincial leaders spoke highly of the Lego Manufacturing Vietnam project, emphasizing its significance. Binh Duong believes that the company will operate effectively and provide high-quality products to both domestic and international markets, meeting stringent standards for precision and excellence. The province hopes that Lego will continue expanding its investment and production in Binh Duong.

Leaders of the province and relevant departments will further support the company, ensuring favorable conditions and promptly addressing any issues that arise to facilitate efficient operations at the factory.

Reported by Ngoc Thanh-Translated by Kim Tin