Redemption of pavement to be finished prior to Tet holiday

Update: 29-11-2012 | 00:00:00

Which items is South Binh Duong Water Environment Improvement project implemented?

The work of building waste water treatment plant has reached 83% of its volume and has been installment of equipments to prepare for a trail by end Nov. and the plant will be handed over by Jan, 2013.

The plant is located at quarter 6, Phu Tho ward, Thu Dau Mot. Network of collection and pump station has reached 80.6% of its plan. The work will be finished by the end of 1st quarter of 2013.   

Could you tell about the project’s advantages and disadvantages?

Our biggest advantage is to enjoy support from the provincial People’s Committee, agencies and sectors as well as people. However, we have faced difficulties such as extension of construction time, change of initial position of pump stations and so on.

How is redemption of pavement implemented, sir?

Redemption of pavement will be implemented in Nov. and ended prior to Tet holiday 2013. Based on the plan, the redemption will end 6 month ahead compared to the contractor’s duration and 18 months ahead from the project’s time.

After construction, road surface will have bad spots, influencing urban beauty. How will be the influence solved?

Redemption of pavement will be divided into 2 phases. Accordingly, the first phase will be implemented temporarily and the 2nd ones will be finished by asphalting.

The investor will steer contractor and consultant unit to render pavement as committed.  

Thanks a lot!

Reported by D.Chi – Translated by A.C    