In 2019, for My Phuoc - Bau Bang route project, Bau Bang District paid 201/206 dossiers for compensation, support, and resettlement (accounting for 97.57%), the remaining 5 dossiers (an area of 3,753.8m2) have not yet received money; 189 cases handed over the sites to investors with an area of 483,334.3m2 (reaching 98.78% total area).For land clearance of 60,602.9m2 of the project in hamlet 6, Hung Hoa commune, the district approved compensation for 14/14 dossiers.
In addition, the district issued notices of land acquisition to implement the construction investment of Bau Bang Industrial Park expansion, the 220kV Chon Thanh - Ben Cat power line. The district also issued a decision on land acquisition and approved the plan for compensation, support and resettlement of Ben Cat 220kV power transformer station.
Reported by Minh Duy - Translated by Ngoc Huynh