Prepare well all aspects for the inauguration ceremony of key projects

Update: 20-09-2024 | 11:25:12

On September 19, Mr. Mai Hung Dung, Member of Provincial Party Standing Committee, Permanent Vice Chairman of the Provincial People's Committee, led a provincial delegation to inspect the preparations for the inauguration ceremony of Bac Tan Uyen - Phu Giao - Bau Bang road, Bach Dang 2 bridge, and the Ho Chi Minh - Thu Dau Mot - Chon Thanh expressway.

Do a good job of preparation

At the People's Committee of Phu Giao district, Mr. Dung, Permanent Vice Chairman of the Provincial People's Committee, listened to the district People's Committee’s reports on the preparations for the inauguration ceremony of the Bac Tan Uyen - Phu Giao - Bau Bang road. Namely, up to now, the district has fully prepared material facilities and is ready to hold the inauguration ceremony well.

Mr. Mai Hung Dung, Permanent Vice Chairman of the Provincial People's Committee, gives a speech at the working session with Phu Giao District People's Committee.

Speaking at the meeting, Mr. Dung appreciated the preparations for the inauguration ceremony by the People's Committee of Phu Giao district, as well as related units. At the same time, he asked the District People's Committee and units to continue coordinating closely so that the inauguration ceremony of Bac Tan Uyen - Phu Giao - Bau Bang road could be carried out in the best way, ensuring great success. He emphasized that the inauguration ceremony must be organized in a solemn, thoughtful, economical, effective and unpretentious manner.

The inauguration ceremony of the Bac Tan Uyen - Phu Giao - Bau Bang road and Bach Dang 2 bridge is expected to take place on the morning of September 23. The event will be held at the intersection between Bac Tan Uyen - Phu Giao - Bau Bang road and Ho Chi Minh - Thu Dau Mot - Chon Thanh expressway.

Previously, Mr. Dung and the provincial delegation surveyed the Bac Tan Uyen - Phu Giao - Bau Bang road. The Bac Tan Uyen - Phu Giao - Bau Bang dynamic road project has a total length of nearly 48km, a scale of 6 lanes, a maximum design speed of 80km/h, a total investment of over 3,800 billion VND, passing through the districts of Bac Tan Uyen, Phu Giao and Bau Bang. This route is invested with the goal of creating a connecting road axis between Bac Tan Uyen - Phu Giao - Bau Bang districts, connecting with Binh Phuoc province. Therefore, traffic connectivity with neighboring areas will be improved, exploiting and serving the travel and freight demands of the people, contributing to the socio-economic development of the two provinces of Binh Duong and Binh Phuoc in general, and the districts of Phu Giao, Bac Tan Uyen, Bau Bang in particular; to gradually complete the province's traffic infrastructure system according to the planning; at the same time to create new momentum for local economic growth.

Regarding the progress of the Ho Chi Minh - Thu Dau Mot - Chon Thanh expressway, Phu Giao district has completed the landmark installation and is currently carrying out land acquisition.

Ready for the inauguration

Binh Duong and Dong Nai provinces are located in the Southern Key Economic Zone. Due to natural conditions, the two provinces are separated by the Dong Nai River. In the past, traffic between the two localities mainly went through Dong Nai bridge (National Highway 1), Hoa An bridge (National Highway 1K), Thu Bien bridge and ferries. Following the socio-economic development trend of the two provinces, especially the two cities - the major administrative and economic centers of the two provinces, Thu Dau Mot and Bien Hoa, the above bridges cannot meet the rapidly increasing traffic demand between the two provinces in particular and the Southeast region in general.

The Bac Tan Uyen - Phu Giao - Bau Bang road project is expected to be inaugurated on September 23.

Mr. Tran Hung Viet, Director of the Provincial Traffic Construction Investment Project Management Board, said that the construction of an additional bridge across the Dong Nai River will first of all facilitate travel for people in the two localities. Besides, transporting goods will be safer than going by ferry and shortening the journey if choosing the traffic direction via Hoa An bridge or Thu Bien bridge. At the same time, the completed project contributes to the complete development of the inter-regional road network in general and between Dong Nai province and Binh Duong province in particular. Bach Dang 2 Bridge project is invested by the Provincial Traffic Construction Investment Project Management Board. The project has a total investment of more than 818 billion VND; of which the approach road is worth more than 327 billion VND, the bridge is worth nearly 491 billion VND. Up to now, the project has been basically completed, ready for inauguration and put into use. 

Reported by Phuong Le - Translated by Ngoc Huynh