Re-monitoring of key public investment projects in North Tan Uyen district

Update: 01-09-2020 | 22:05:03

 On August 27, Supervision delegation of Provincial People's Council led by Nguyen Tam Duong, Head of Economic and Budget Board of Provincial People's Council, re-monitored the implementation of DT747a Road upgrading and expanding project (the section from Ba Nghia slope to Cong Xanh junction); projects of central area and overall technical infrastructure, memorial of War Zone D. These are two key public investment works of the province invested by Provincial Construction Investment Project Management Board. 

The supervision delegation checked the implementation of DT747a road upgrading and expansion project from Ba Nghia slope to Cong Xanh junction.

DT747a road upgrading and expansion project has a total investment of more than VND509 billion. Project implementation period is from 2013 to 2021. Bidding packages 1, 3, 4, 5 and 6 handed over the completed works to management units.

This project has a total investment of nearly VND392 billion. So far, aesthetic work has been carried out to finish this project. The core of monument is completed.

At the working session, the delegation noted difficulties and suggestions of investors to report to Provincial People's Council.

Reported by Phuong Le - Translated by Ngoc Huynh