Binh Duong Power Company to ensure power supply in the dry season

Update: 15-03-2019 | 11:59:27

According to the calculation of the electricity industry, the annual demand for electricity in the province increased by about 10%. Every year, to meet the demand for electricity use, the electricity industry has organized surveys and assesses customers' demand for electricity in order to promptly invest in new ones as well as upgrade transformer stations to ensure the supply capacity of quality, stable power source for customers.

T1 substation works promptly put into use in the dry season 2019, contributing to ensuring a stable source of electricity for production and business of enterprises. Photo: Minh Duy

In the dry season of 2018, the survey collected opinions from customers in Binh Duong new city area, especially Dai Dang, Kim Huy, Song Than 3 industrial parks (IPs) showing the need to use electricity. The production and business cases of enterprises face many difficulties when the quality of electricity is unstable. Due to overload, the voltage quality is unstable, sometimes the power failure due to overloading affects the production activities of the enterprise. Some businesses in the electronics industry are worried about the unstable power quality that could cause damage, affecting production stages and lines.

Mr. Le Minh Quoc Viet, Director of Binh Duong Power Company (PCBD), said that he received feedbacks and suggestions from customers, PCBD cooperated with Southern Power Corporation to quickly survey to catch up. At the time of implementing the investment of T1 Tan Hiep substation in Phu Tan ward, Thu Dau Mot city to reduce the load for neighboring transformer stations, ensuring a stable quality power supply for businesses and residents at Binh Duong new city area.

Mr. Nguyen Duy Hieu, Deputy Director of PCBD, said that 110kV T1 substation and connection line were built in Phu Tan Ward, Thu Dau Mot City invested by Southern Power Corporation with JICA loan. of Japan with a total investment of VND 76.2 billion to supply electricity for industrial and living areas in Thu Dau Mot City and surrounding areas with scale including: New construction of 110kV line, 2 circuits, 2.86 km long and 2 x 63MVA 110kV substation. In which, the first phase installed a 63MVA transformer and is continuing to invest in installation of transformer No. 2.

“With a period of 3 months to build, complete and close the electricity and put it into use in the dry season, 2019 is a“ miracle ”as well as the efforts and determination of the participating units. In the process of implementing the project, there were many difficulties such as compensation and site clearance, in particular there were cases that hindered construction units. However, thanks to the active attention and support from the provincial People's Committee and the authorities of Thu Dau Mot City in mobilizing people to hand over the construction site, the project has been completed as scheduled. "Mr. Nguyen Duy Hieu shared.

Under the direction of the Provincial Party Committee, the Provincial People's Committee, the supply of electricity to the Industrial Complex - Services and Urban areas is very important, however, in the past, the substations for the area are always full of load, not satisfying enough demand for the entire load in the area. In recent years, with the rapid growth of industry and urban areas, the demand for electricity in daily life, production and business in the province has increased by more than 10% on average. Southern Power Corporation, PCBD has timely surveyed and invested a lot of power projects, power stations to meet the load demand in the region. Operation and use of Tan Hiep T1 station contributes to reducing the load for surrounding stations such as: Khanh Van Station; Station T4; T5, Bau Beo and VSIP stations expanded.

Mr. Tran Quang Vinh, Manager of Dai Dang Industrial Zone Management Board, said that in 2018, when no T1 station was built, electricity in the IP was very unstable and unstable. Since the T1 substation works, the power source always ensures to meet the electricity needs of enterprises in the IZ and neighboring electricity users because most businesses use a lot of machines and equipment. electronics, so I want to have a stable power source.

“Entering the dry season in 2019, with the electricity sector put into operation, 100kV T1 Station, businesses are very excited because the power source will be stable, ensuring continuous production without interruption affecting production and business activities of enterprises ”, Mr. Vinh said.

It can be said with the efforts of the Southern Power Corporation, Southern Power Project Management Board, PCBD and the close and fierce attention of the Provincial Party Committee, People's Committee of Binh Duong province and the close coordination. with Binh Duong Provincial Public Security, Thu Dau Mot City People's Committee, Phu Tan Ward and related departments organize construction protection forces, contributing to the completion of the project on schedule and put into operation and security, ensuring overload for 110 kV substations in the area, ensuring safe and continuous power supply for industrial production and daily life in Thu Dau Mot City and surrounding areas in the province Binh Duong.

Reported by Minh Duy – Translated by Vi Bao

 