In 2024, the public investment plan of Ben Cat city is 456 billion VND, of which, the city has up to now disbursed 263 billion, achieving 57.76% of the annual plan.
To achieve the target for 2024, the city has recently organized the signing of agreements and launched a movement to accelerate the disbursement of public investment capital in 2024. Along with that, the functional departments and localities of the city are monitoring and grasping the implementation of public investment projects, strengthening the inspection of the progress of key projects; doing well in investment preparation; at the same time, appraising and approving contractor selection plans, approving projects. The functional departments also develop plans for implementation, monitor the progress of land clearance for each specific project; timely compensate and clear land immediately after the unit price is approved.
Reported by Tuan Anh – Translated by Vi Bao